Building Permits Frequently Asked Questions
What is the review period for Building Permit Applications?
The time required for processing a Building Permit application is between 10 to 30 business days, depending on its class and size determination as follows:
10 days |
Houses and semi-detached houses including:
|
15 days |
|
20 Days |
|
30 days |
|
The above timelines are for complete permit applications. A complete application is one that meets zoning requirements, all applicable laws & the submitted drawings provide all the required information.
Please be advised that Staff will provide assistance to the applicant but must refrain from acting in the capacity of a designer.
How long is my permit valid?
You have six months after the permit is issued to start construction. Once construction commences, the permit will not expire, although, it can still be revoked as per section 8 of the Building Code Act if construction discontinues for more than one year