Inspections
Inspections do not happen automatically.
It is the homeowner's or contractor's responsibility to contact the County of Brant to book an inspection. Failure to have inspections may result in uncovering and exposing work for inspection.
Building inspections must be booked with a minimum of 24 hours notice and prior to 3:00 pm to receive an inspection for the following business day (subject to availability). Any inspections booked after 3:00 pm will be booked for the second following business day.
How to book an Inspection
To book an inspection, fill out the Inspection Request online below. Please do not directly contact the Inspector.
To cancel an inspection, contact the Building DivisionYou'll need to provide the following information:
- Project address
- Contact name and telephone number
- Type of inspection
- During the inspection process:
- The approved permit drawings must be on site
- The permit must be posted on site
- 24-hour notice must be given for building inspections
- Do not cover or continue construction until each inspection stage is reviewed
- An inspection is required prior to the occupancy of a building
- A final inspection is required to close a building permit
Inspection Stages |
A Building Inspector will be required to review your project in several stages during construction. These stages are typically listed as required inspections on the issued building permit. When conducting the mandatory inspections, the building inspector must be able to see that part of work under inspection. Stages include:
No occupancy permitted until occupancy/final inspection has been completed and passed. |
Additional Re-inspection Fees |
Where an Inspector determines that work for the stage of construction that has been requested to be inspected is not substantially complete, is not ready for an inspection or where previous infractions have not been addressed. |