Main Street and Dumfries Street, Paris - Reconstruction
The reconstruction of Dumfries Street from Main Street to the dead end, and of Catherine Street from Dumfries Street to Washington Street is anticipated to start on or about Monday, July 21, 2025. The work is expected to take approximately 12 weeks to complete.
Phase 1 – July to October 2025:
- Dumfries Street from Main Street to the dead end
- Catherine Street from Dumfries Street to Washington Street
Phase 2 – October to December 2025:
- Main Street from Washington Street to Creeden Street
Project Contractor: Oxford Civil Group
Details:
The scope of work for Phase 1 includes but is not limited to:
- Installation of new watermain on Dumfries Street and Catherine Street
- Storm sewer adjustments on Dumfries Street
- New storm sewer on Catherine Street
- Removal of the existing sidewalk on the west side of Dumfries Street
- Removal and replacement of sidewalk on the east side of Dumfries Street
- New concrete curb and gutter on Dumfries Street and the north side of Catherine Street
- New asphalt
The reconstruction of Main Street from Washington Street to Creeden Street will start once the base lift of asphalt on Dumfries Street has been placed. The work on Main Street is expected to take approximately 11 weeks to complete.
The scope of work for Phase 2 includes but is not limited to:
- Installation of new watermain from Washington Street to Creeden Street
- New storm sewer between Washington Street and Ball Street
- Installation of new sanitary sewer from Ball Street to Creeden Street
- Removal of existing sidewalk on the south side of Main Street from 27 Main Street to Ball Street
- Removal and replacement of sidewalk on the north side of Main Street between Washington Street and Ball Street, and on the south side of Main Street between Washington Street and 27 Main Street
- New concrete curb and gutter on Main Street from Washington Street to Ball Street
- New dedicated parking area on the north side of Main Street
- New asphalt
Please refrain from parking on the street within the project limits during each phase. Residents are encouraged to park in their driveways or in the designated parking areas on Main Street, Queen Street and Washington Street. If you must park within the project limits, please remove your vehicle by 7:00 am to allow for work to continue without disruption.
During construction, any privately-owned infrastructure (irrigation: sprinklers, sprinkler heads/hose, etc.), landscaping (gardens, etc.), and decorations in the right of way may be damaged. Residents are responsible to relocate, remove and/or repair anything that is in the right of way during construction. If any of the items listed above are relocated within the right of way and become damaged during construction, it is solely the resident’s responsibly to restore and/or repair. The County is only responsible for repairing driveways and lawns (topsoil and sod).
While your street is closed to through traffic during construction, garbage trucks will not be permitted to enter the project limits. The Contractor will be responsible for collecting your garbage and recycling on the day of pickup. To ensure your garbage and recycling get collected each week, garbage and recycling must be placed curbside by 7:00 am. Mark your bins with your street address so that they can be returned to the correct property by end of day.
During construction, additional notices will be delivered at key milestone events (e.g. water shutdowns, concrete curb placement, sidewalk installation, asphalt paving and sod installation). Please monitor your mailbox throughout construction to stay informed. You can also visit www.brant.ca/roadclosures for all project notices. Please refer to Municipal511 https://www.municipal511.ca for the most up-to-date information regarding road construction and closures.
It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated.