Road Closures and Construction

The County is responsible to build, maintain and repair roads, sidewalks and other infrastructure. We make every reasonable effort to notify you about road closures in advance of any disruption. However, all dates are tentative and may change without notice. The County inspects and maintains the streets regularly according to the Minimum Maintenance Standards set out by the Province. 

On this page:

  • Current road construction map
  • List of current road closures and construction 
  • Construction zone safety
  • What to expect during construction
  • Report a problem 

Current Road Construction Map

Temporary road closures and construction

King Edward Street Construction September 26 and 27 - lane closures

Location: King Edward Street between Hanlon Place and Church Street

Work Dates: Tuesday September 26 and Wednesday September 27, 2023

Work Preformed by: Sierra Infrastructure Inc. for County of Brant

Reason: Curb placement King Edward Street and Dundas Street West intersection

Note:

Through traffic will be maintained

Local access will be maintained

Emergency access will be maintained

Signage will be posted, and a flag person will direct traffic when required

 

Please refer to Municipal 511 http://www.municipal511.ca for the most up-to-date traffic information regarding road construction and closures.

 

It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated. If additional information is required, please contact:

 

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue

Burford ON N0E 1A0

519.449BRANT X2209

publicworks@brant.ca

 

Gessele Dinsay

Inspector

County of Brant

26 Park Avenue

Burford ON N0E 1A0

519.449BRANT X2209

publicworks@brant.ca

McLean School Road Gravel to Hardtop

Location: McLean School Road, from Hwy #24 to 300m West of Hwy #24 

Work Dates:  Monday, September 11 for approximately 2 weeks

Notes: 

  • McLean School Road will have one lane open during working hours and will be open overnight and weekends.
  • Daytime traffic will be controlled by Traffic Control Personnel.
  • The road will be gravel surface during construction.   

Please refer to Municipal 511 http://www.municipal511.ca for the most up-to-date traffic information regarding road construction and closures.

It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated.


Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue

Burford, ON N0E 1A0

519. 44B.RANT x2209

publicworks@brant.ca  

 

Javier Marcos, C. Tech

Senior Engineering Technologist

County of Brant

26 Park Avenue

Burford, ON N0E 1A0

519. 44B.RANT x2031

publicworks@brant.ca



Race Street, Paris - Temporary Road Closures for construction - Update - September 26-27

Location: Between 125 and 127 Race Street

 

Work Dates: Tuesday September 26 5:00 p.m. to Wednesday September 27 7:00 a.m.

Work Preformed by: Beech Infrastructure Group for County of Brant

Reason: Sanitary main replacement at Race Street

Note:

  • No through traffic, no local or emergency traffic
  • 111-125 Race Street accessible from Old Mill Street, Ball Street, and Gilston Parkway
  • 127-146 Race Street accessible from Hillside Avenue and Gilston Parkway

 

Please refer to Municipal 511 http://www.municipal511.ca for the most up-to-date traffic information regarding road construction and closures.

 

It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated. If additional information is required, please contact:

 

Joe Murphy, C.E.T.                          

Capital Project Manager

County of Brant

26 Park Avenue

Burford ON  N0E 1A0

519.449BRANT X2209

publicworks@brant.ca

Emily Somerville

Junior Engineering Technologist

County of Brant

26 Park Avenue

Burford ON  N0E 1A0

519.449BRANT X2302

publicworks@brant.ca

Iarocci Boulevard, Paris - Road Construction, Sanitary Sewer, Watermain, Stormwater Works
  • From Consolidated Drive to Green Lane
  • Consolidated Drive from Iarocci Boulevard to 200m north-west

Dates: Monday, July 17 to Friday, December 15, 2023

Duration: 5 months

Reason: New Road Construction including Sanitary Sewer, Watermain, Stormwater Works

Road Access:

  • Consolidated Drive near Iarocci Blvd will occasionally be closed to traffic for watermain and sewer installation work.

  • Local and emergency traffic will be accommodated at all times

  • road will be open overnight and on weekends.

  • Daytime traffic controlled by Traffic Control Personnel

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Hillside Avenue and Race Street, Paris - Sanitary Sewer Replacement and Sidewalk Installation

  • From south of Old Mill Street to Ball Street

Dates: Monday, June 5 to Friday, December 1, 2023

Duration: 6 Months

Reason: Sanitary Sewer Replacement and Sidewalk Installation

Road Access: 

  • no through traffic
  • local and emergency access only
  • Traffic Control Personnel during daytime operations
  • road will be gravel surface during construction

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Grand River Street North, Paris - Trunk Sewer and Watermain Replacement 

  • From Silver Street to Scott Avenue

Dates: Tuesday, August 8 to Friday, December 15, 2023

Duration: 6 Months

Reason: Trunk Sewer and Watermain Replacement

Road Access: 

  • No through traffic
  • Local access will be maintained
  • Emergency access will be maintained
  • Grand River Street North will be reduced to one lane, one way, in the southbound direction. All northbound traffic will be detoured along Silver Street, Oak Avenue and Scott Avenue. Intersection closure will occur when required. 

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Dundas Street West, Daugaard Avenue, Chapel Street, and Main Street in Paris - Water, Sewer, Road Construction

  • Dundas Street West between King Edward Street and 77 metres east of Chapel Street
  • Daugaard Avenue between Dundas Street West and 95 metres south
  • Chapel Street between Dundas Street West and south end
  • Main Street between Chapel Street and 37 metres east of Washington Street

Dates: Tuesday, May 23 to December 2023

Duration: TBD

Reason: Trunk watermain replacement, storm sewer extension, and road work including sidewalk installation

Road Access:

  • No through traffic
  • Local access will be maintained
  • Emergency access will be maintained
  • Signage will be posted, and a flag person will direct traffic when required
  • Non-local motorists are encouraged to take alternative traffic route

 

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Surface Treatment Replacement or Resurfacing Low Volume Roads  - Various locations

  • Bethel Church Road from Governors Road East to Bethel Church Road
  • East Quarter Townline Road from 1.0 km north of Ninth Concession Road to Eighth Concession Road
  • Eighth Concession Road from Harley Road to East Quarter Townline Road (north Leg) to Kloepfer Road to West Quarter Line Road to Muir Road South to Kloepfer Road to Middle Townline Road to Harley Road
  • Fairfield Road from Roswell Road to Middle Townline Road
  • Fifth Concession Road from Lawrence Road to Middle Townline Road
  • Glen Morris Road East from Highway #24 to 1.77km east of Highway #24
  • Harrisburg Road from German School Road to 180m north of German School Road to 180m North of German School Road to Brant/Hamilton Boundary
  • Hatchley Road from Williams Road to Middle Townline Road
  • Johnson Road from 170m south of Adams Road to Brant County Road #18 to Lynden Road to Adams Road
  • McPherson School Road from Blue Lake Road to Scenic Drive to Scenic Drive to McLean School Road to McLean School Road to Glen Morris Road East
  • Paris Plains Church Road from Pinehurst Road to 1.2km east of Pinehurst Road to 1.2km east of Pinehurst Road to West River Road to Ayr Road to Pinehurst Road
  • Robinson Road from Pottruff Road to Greens Road
  • Second Concession Road from Etonia Road to Maple Avenue North
  • Sixth Concession Road from 600m east of Lawrence Road to Middle Townline Road
  • Tenth Concession Road from Middle Townline Road to East Quarter Townline Road (north leg) to East Quarter Townline Road (north leg) to Maple Avenue South
  • Third Concession Road from Etonia Road to Maple Avenue North to Etonia to Middle Townline Road
  • Thirteenth Concession Road from East Quarter Townline Road (west leg) to Maple Avenue South
  • Twelfth Concession Road from East Quarter Townline Road to Maple Avenue South
  • Wetmores Road from 0.2 km east of Mount Pleasant Road to Biggars Lane
  • Hammond Road from McBay Road to Brant School Road


Dates:  Monday May 29 to Friday September 29

Duration: 4 Months Approximately 

Road Access during construction:

  •  No through traffic
  • Local access will be maintained
  • Emergency access will be maintained
  • Signage will be posted, and a flag person will direct local and emergency traffic when required
  • Caution: road will be gravel surface during construction

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca                                     

 

Javier Marcos C. Tech

Senior Engineering Technologist

County of Brant

26 Park Avenue

Burford, ON N0E 1A0

519. 44BRANT x2031

publicworks@brant.ca

Pavement Markings - retracing existing stop bars, crosswalks, turning arrows, parking stalls and centerline paint
  • Various locations

Dates: Monday, April 24 to Friday, September 29

Duration: 4 Months

Road Access:  

  • Through traffic - stay back from line painting vehicles 

  • Obey posted signage

Javier Marcos C. Tech

Senior Engineering Technologist

County of Brant

26 Park Avenue

Burford, ON N0E 1A0

519. 44BRANT x2031

publicworks@brant.ca

McMillian Road, Brantford - McMillan Bridge Rehab

  • From Powerline road to Lynden road

Dates: Monday, April 24 to Friday, November 10, 2023

Duration: 6 Months

Reason: McMillan Bridge Rehab

Road Access: 

  • No through traffic

  • Local access will be maintained

  • Emergency access will be maintained

  • Detour route will be posted

  • The road and bridge between 30 and 63 McMillan Road will be closed to all traffic
  • Access to 4 to 30 McMillan Road will be from Lynden Road
  • Access to 56 to 121 McMillan Road will be from Powerline Road

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Glen Morris Road East, Glen Morris - Glen Morris Road Bridge Rehab

  • From Branchton Road to Tanner Road

Dates: Friday, June 9 to Thursday, November 30, 2023

Duration: 6 Months

Reason: Glen Morris Road Bridge Rehab

Road Access: 

  • No through traffic

  • Local access will be maintained

  • Emergency access will be maintained

  • Detour route will be posted

  • One lane of traffic will be maintained on the road and bridge between 61 Glen Morris Road East and Branchton Road intersection. Signage will be erected. Traffic control personnel will direct traffic when necessary.

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Pauline Johnson Road, Middleport - VanSickle Bridge Rehab

  • From Big Creek Road to Baptist Church Road

Dates: May 19, 2023 to late fall

Duration: 6 Months

Reason: VanSickle Bridge Rehab

Road Access: 

  • No through traffic
  • Local access will be maintained
  • Emergency access will be maintained
  • Detour route will be posted
  • The road and bridge between 85 and 100 Pauline Johnson Road will be closed to all traffic. 

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Burtch Road, Mt. Pleasant - Cook Bridge Rehab

  • From Pleasant Ridge Road to Mt. Pleasant Road

Dates: Wednesday, May 10 to Friday, October 20

Duration: 5 Months

Reason: Cook Bridge Rehab

Road Access: 

  • Road access over Cook Bridge  closed to all through traffic 
  • Detour signage posted 
  • Local and Emergency access to 533 through 607 Burtch Road from Mt. Pleasant Road
  • Local and Emergency access to 612 through 661 Burtch Road from Pleasant Ridge Road

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca
Cleaver Road, Mt. Vernon - Cleaver Road bridge closed for assessment

Cleaver Road from Robinson Road to Highway 53

Dates: July 17, 2023 until further notice

Reason: Cleaver Road bridge closed for assessment

Road Access: 

  • no through traffic over bridge

Joe Murphy, C.E.T.

Capital Project Manager

County of Brant

26 Park Avenue                                              

Burford, ON N0E 1A0                                      

519. 44BRANT x2209                                      

publicworks@brant.ca

Salt Springs Church Road, Onondaga - Road Issue
  • From Brant County Road 18 to Hamilton Road

Dates: Wednesday, April 7, 2022 until Further Notice

Reason: Road Issue

Road Access: 

  • No through traffic, local and emergency traffic only

Brant Mill Road, Oakland - Brant Mill Bridge structural assessment

  • From 14 Brant Mill Road between Oakland Road and Jenkins Road

Dates: Friday, October 19, 2018 until further notice

Reason: Brant Mill Bridge structural assessment

Road Access:

  • No through traffic
  • Detour routes will be posted 
Governors Road West, Paris - Construction
  • At Cleaver Road

Dates: Effective September 30, 2013 until further notice

Reason: Construction

Road Access: No through Traffic 

Construction zone safety

  • Do not enter if a "Road Closed" sign is present
  • Be extra cautious and slow down as vehicles ahead could stop suddenly
  • Watch for the person directing traffic
  • Ontario Provincial Police (OPP) would like to remind motorists to be extra cautious while travelling in construction zone and fines may increase

What to expect during construction

  • Delays
  • Loss of access to your road for a short period of time
  • Place your garbage and recycling at the curb, as usual, unless otherwise notified

Report a problem

If you notice something that needs to be fixed on a County of Brant Road, report it below.

Report 

Contact us.

We're here for you.

Call us at 519.442.7268
519.44BRANT (519.442.7268) 1.855.44BRANT
Email the County of Brant
Email
Visit a Customer Service Office
Visit
Report a problem in the County of Brant
Report a problem

Follow us. We're social!

  • View County of Brant Facebook page
  • View County of Brant Twitter page
  • View County of Brant Instagram page
  • View County of Brant YouTube page

County of Brant logo

  • Accessibility
  • Freedom of Information and Protection of Privacy
  • Careers
  • Sitemap
  • Website Feedback

© 2022 County of Brant

By GHD Digital

Browser Compatibility Notification

It appears you are trying to access this site using an outdated browser. As a result, parts of the site may not function properly for you. We recommend updating your browser to its most recent version at your earliest convenience.