Good news, Paris! The multi-year infrastructure project continues to move right along as we wrap up major underground work. Here is a quick look at where things stand and what to expect next:
What’s Done and Underway:
- Paris Road: Open to two-way traffic. Underground pipes and base asphalt are done, sidewalks/curbs are 75% complete, and the sanitary forcemain is almost finished (95%).
- Governors Road East: Eastbound underground work, concrete, and base paving are complete.
- Dundas Street East: Major underground pipes, watermain near the CN Bridge, and base paving are complete. Crews are currently working on curbs, sidewalks, and paving entrances.
Heads Up — Upcoming Detour:
- Governors Road will soon be reduced to one-way traffic (westbound only) for approximately 4 weeks (weather dependent) for sanitary sewer installation. Eastbound traffic will follow a posted detour. We’ll share an update as soon as the start date is confirmed.
Looking Ahead:
- Late Fall 2026: Wrapping up major underground utility work and excavation for the season (pending weather, a final storm sewer connection may shift to the spring).
- Spring 2027: Crews will return for the final layer of asphalt, remaining sidewalks/curbs, and landscaping restoration.
Thank you for your continued patience and for driving safely through the construction zones.
To learn more about this project and receive updates, subscribe to www.EngageBrant.ca/DundasEast.
Sign up for County of Brant News
Stay up to date on County of Brant activities, events, programs, and operations by subscribing to our news updates.