Construction Update: Dundas St E, Paris Rd and Oak Park Rd

Good news, Paris! The multi-year infrastructure project continues to move right along as we wrap up major underground work. Here is a quick look at where things stand and what to expect next:

What’s Done and Underway:

  • Paris Road: Open to two-way traffic. Underground pipes and base asphalt are done, sidewalks/curbs are 75% complete, and the sanitary forcemain is almost finished (95%).
  • Governors Road East: Eastbound underground work, concrete, and base paving are complete.
  • Dundas Street East: Major underground pipes, watermain near the CN Bridge, and base paving are complete. Crews are currently working on curbs, sidewalks, and paving entrances.

Heads Up — Upcoming Detour:

  • Governors Road will soon be reduced to one-way traffic (westbound only) for approximately 4 weeks (weather dependent) for sanitary sewer installation. Eastbound traffic will follow a posted detour. We’ll share an update as soon as the start date is confirmed.

Looking Ahead:

  • Late Fall 2026: Wrapping up major underground utility work and excavation for the season (pending weather, a final storm sewer connection may shift to the spring).
  • Spring 2027: Crews will return for the final layer of asphalt, remaining sidewalks/curbs, and landscaping restoration.

Thank you for your continued patience and for driving safely through the construction zones.

To learn more about this project and receive updates, subscribe to www.EngageBrant.ca/DundasEast.  

Sign up for County of Brant News

Stay up to date on County of Brant activities, events, programs, and operations by subscribing to our news updates.